After visiting site on the 31st August, we are happy to report that the brickwork is currently up to first floor level in most places, and the black glazed blocks are starting to be laid. The roof is nearly complete, with the final touches being added.
Here are some photos of our new office in progress:

Front elevation

Ground floor interior

First floor interior with our team showing the new size of our personal working space

Beautiful view from our new office

Roof in Progress

We have been learning a lot from every site visit

Surroundings
Time-lapse Video: Vimeo.com
Live Photography: SGP New Offices Timelapse